BoM risk register and weekly report
Every engagement keeps one risk register: one line per part that could stall the build, with a candidate remedy, the change it would need, an owner and a date. Each week the client gets a short written report built from it. Both live in the client portal; here is a sample of each.
1 · Risk register
Example Wearables · wrist sensor · EVT rev C · build of 300 units · target build Jan 12
| Ref | Part | Qty/unit | Lead time | Sources | Risk | Candidate & change needed | Owner | Next step | Due |
|---|---|---|---|---|---|---|---|---|---|
| U7 | MAX30101EFD+T Optical AFE · Active | 1 | 26 wk | 1 | High | Alternate optical AFE (two candidates) Footprint change + optics re-validation | Client EE | Pick one candidate for the DVT spin | Nov 14 |
| U3 | LSM6DSOXTR 6-axis IMU · Active | 1 | 18 wk | 1 | High | BMI270 Same package; firmware driver change | Client FW | Bring up BMI270 on 5 EVT boards | Nov 21 |
| U12 | DRV2605LDGSR Haptic driver · Active | 1 | 22 wk | 1 | High | Second-source haptic driver Pin-compatible check + tuning | HyphenHW | Confirm pinout and samples | Nov 7 |
| U1 | NRF5340-QKAA-R7 SoC / BLE · Active | 1 | 12 wk | 2 | Watch | None needed No design change | HyphenHW | Place order 8 weeks before build | Nov 3 |
| U9 | SI7021-A20-GM1R Humidity sensor · Active | 1 | 16 wk | 2 | Watch | SHT40 (candidate) Footprint change | Client EE | Decide keep vs. switch at DVT | Dec 5 |
| C14–C40 | GRM155R61A105KE15D MLCC 1 µF 0402 · Active | 27 | 2 wk | 3+ | Low | — — | HyphenHW | Buy with main order | — |
Risk is scored on six dimensions: lead time against the build date, sourcing concentration, lifecycle, inventory depth, allocation history and substitution difficulty.
2 · Weekly status report
To: Example Wearables hardware team · From: HyphenHW · Week of Nov 2 (sample)
Summary
The build is on track for Jan 12 if two decisions land this week. Three parts are past the build date at today’s lead times; two have candidate alternates in evaluation and one needs an order placed now.
Decisions we need from you
- Optical AFE (U7): choose one of the two candidates for the DVT spin, by Nov 14. Both need a footprint change; datasheets and the comparison are in the portal.
- PO approval: nRF5340, 330 pcs (300 + 10% build allowance), via your authorized distributor account. Ordering by Nov 3 keeps 4 weeks of margin.
Orders
| Part | Qty | Status | Expected |
|---|---|---|---|
| NRF5340-QKAA-R7 | 330 | Awaiting your approval | Dec 29 |
| GRM155R61A105KE15D | 9,000 | Ordered | Nov 18 |
Changes since last week
- DRV2605L quoted lead time moved from 18 to 22 weeks; second-source samples requested.
- BMI270 bring-up started on 5 EVT boards (your firmware team); first readings expected Nov 10.
Next week
- Confirm the haptic driver pinout and samples.
- Re-check lead times on all High and Watch lines.